Rescuing a Mission-Critical SAP-to-NAXT 365 ERP Transformation in Just Four Months

4Months to Go-Live
130+Data Entities Migrated
MultipleLegal Entities
SpanishLocalized Delivery
GECOLSA material-handling equipment

Customer Overview

GECOLSA is one of Colombia's leading distributors of heavy equipment, machinery, power systems, and aftermarket services. Operating across multiple legal entities, the organization supports complex sales, service, inventory, finance, and supply chain operations throughout the country.

As part of its digital transformation strategy, GECOLSA embarked on a migration from SAP to NAXT 365. However, after nearly two years of implementation, the project had stalled. The implementation partner had withdrawn due to the complexity of the engagement, leaving the customer just four months away from its planned go-live with an incomplete migration program.

The Challenge

By the time LGSTech was engaged, the ERP implementation had become a high-risk rescue project.

The organization faced several critical challenges:

Nearly two years of implementation delays with limited migration progress

Previous implementation partner exited the project due to its complexity

Only four months remained before the committed go-live date

Migration from SAP to NAXT 365 across multiple legal entities

More than 130 business-critical data entities requiring migration

Legacy business data stored in SQL databases with varying structures and quality

Spanish-language implementation requiring localized business processes and data handling

Business requirements continued to evolve, increasing migration scope during execution

The customer needed a partner capable of rapidly assessing the existing environment, recovering the migration program, and delivering a reliable data foundation without delaying the ERP deployment further.

The Solution

LGSTech began the engagement with a comprehensive discovery and migration assessment to evaluate the existing implementation, understand legacy SQL data structures, identify data quality issues, and determine the work required to recover the project.

Using LGSTech's data migration solution, the team established an automated migration framework that accelerated data extraction, transformation, validation, and loading while reducing manual effort and migration risk.

The engagement included:

01

Comprehensive migration discovery and assessment

02

Automated extraction from legacy SQL databases

03

Data cleansing, profiling, and transformation

04

Migration of more than 130 data entities

05

Cross-entity dependency management

06

Multi-legal entity migration planning and execution

07

Automated validation and reconciliation

08

Iterative migration testing and business verification

09

Controlled management of increasing project scope throughout the engagement

The automation-led approach enabled rapid execution while maintaining data quality, governance, and business continuity.

The Results

Despite inheriting a stalled implementation with a highly compressed timeline, LGSTech successfully stabilized the migration program and enabled the customer to move forward with its planned ERP deployment.

Business Outcomes

Rescued a stalled ERP implementation after nearly two years of delays

Executed the migration program within the remaining four-month go-live window

Successfully migrated 130+ business-critical data entities

Supported migration across multiple legal entities

Accommodated expanding project scope without disrupting delivery timelines

Improved data quality through automated validation and reconciliation

Reduced migration risk and restored confidence in the ERP transformation program

Why LGSTech

Large-scale ERP transformations often succeed or fail based on the quality and execution of the data migration strategy. Rescue projects, in particular, demand rapid assessment, deep migration expertise, and proven automation capabilities.

By combining a structured migration methodology with LGSTech's data migration solution, the team successfully recovered a complex SAP-to-NAXT 365 implementation, delivering a reliable migration foundation within an aggressive four-month timeframe.

At a glance

Project Snapshot

Key engagement details, scope, and delivery context.

CustomerGECOLSA
IndustryHeavy Equipment Distribution
Source ERPSAP
Target ERPNAXT 365
Migration Scope130+ Data Entities
Legacy DatabaseSQL Server
Legal EntitiesMultiple
LanguageSpanish
Project TypeERP Migration Rescue
Engagement Timeline4 Months Before Planned Go-Live
SolutionLGSTech's Data Migration Solution